Buildings in Japan cut their power for electrical inspections and maintenance, usually over a night or a weekend. Someone has to shut the tenant's IT down in the right order beforehand, bring it back afterwards, and prove it works before staff return. eSolia does this several times a year, for almost all of its clients. This story combines four of those outages, from 2020 to 2026: a law firm's server room, an office shared by two affiliated companies, a manufacturer's office, and a medical device maker's distribution warehouse.
Project parameters
| Parameter | Value |
|---|---|
| Engagements | 4 planned outages (2 in 2020, 2 in 2026), out of the several we handle every year |
| Sites | 3 offices and 1 distribution warehouse in Japan |
| On-site team | 1 eSolia engineer per outage, working with client staff and the client's IT teams overseas |
| Visits | 2 per outage (shutdown and restart), from 30 minutes to about 3 hours each |
| IT powered off | From about 16 hours overnight to a full weekend |
What needed solving
In all four cases the client's IT team was overseas, in New York or elsewhere in the Asia-Pacific region. Some of the work can be done from there: at the shared office, the New York team shut down the virtual machines itself. But nobody overseas can press a power button, pull a cable or read an LED. The building sets the outage time and doesn't move it.
Each site had its own complication. The law firm's server room held two rack UPS units, storage, virtualization hosts, firewalls and two phone systems, and its change request came from head office with a conference call attached. The shared office had two sets of servers and network equipment, per company, in server room. The warehouse couldn't stop its IT until both floors had finished the day's operations.
What we did
Preparation. We told users and the overseas IT teams the schedule in advance, and confirmed the procedure and the validation list. At the manufacturer's office we booked the phone system's maintenance vendor for the same window. At the shared office we updated the network diagram two days before, and collected the building's security instructions so we could let ourselves in and out.
Shutdown. Each site had its own order. The law firm's, set by head office, was telecom, then servers, then network equipment, then the UPS. Where the server room has its own breaker, that goes off last, after the UPS. A smaller installation often has a dedicated circuit that runs from the building's breaker panel straight to the rack, but a larger has a breaker in the room; at the law firm we switched off the wall breakers both UPS units were down. At the shared office we waited for New York to confirm the virtual machines were down before touching the hosts. At the law firm and the shared office we then pulled the power cables from the equipment, labeling any that weren't labeled, so nothing could start by itself when the building's power came back. At the law firm, the office's staff forwarded the lawyers' phone lines to a mobile for the duration.
Restart. Power comes back in the reverse order: the room breaker first where there is one, then the UPS, then everything else. At the law firm we switched the wall breakers back on as soon as the building announced that power was restored, then started the two UPS units. At the shared office the procedure had us wait a minute after the internet line terminal before powering on the firewall. We checked for error LEDs and abnormal noise as equipment came up, and at the law firm each head-office team confirmed its systems in turn.
Validation. Each site had a written list; the longest had seventeen checks. They covered wired and wireless network, file shares, email in both directions, internet and intranet, printing, scanning and fax, desk phones for inbound and outbound calls, and the door card readers. At the law firm, a member of the office staff worked through the PC checklist with head office. At the manufacturer's office and the warehouse, we told users when the work was complete.
What went off-plan
Three of the four outages had something the plan didn't cover.
At the law firm, the team that manages the phone system shuts it down remotely, and this time it wouldn't go down. On their instruction we held its power-down button for ten seconds, until the LED showed it was safe to remove power. The conference call couldn't be reached from the server room phone by any dialing pattern we tried, so the moderator in the United States dialed us in instead, which made the start late. After the restart, test PC wouldn't power on from any outlet. And the server room's main air conditioner was already faulty that weekend, so the building's HVAC team came after power-up to check the temporary unit.
At the warehouse, the building's maintenance overran. Our engineer waited outside for 30 minutes before the restart could begin.
At the manufacturer's office, a few people were still in an meeting at shutdown time. We waited for it to end.
None of these stopped the restart. They're the reason someone is on site.
What the clients gained
- Systems restarted and validated at all four sites
- A written report after each outage, in English, for the client and its overseas IT team
- Follow-up actions on record: the law firm's report listed five, including a decision on the dead test PC, a de-rack and disposal request for a retired server, and a note to change the conference call arrangement for the next outage
- At the warehouse, remote standby the next morning, and confirmation from users that the environmental monitoring system was reporting normally
For how we plan these events, see Building Power Outage IT Management.
Projects in this story