Shut down and restart an office's IT equipment around the building's annual power outage, in a fixed order, with the phone system vendor coordinated in advance.

  • Notified users and the regional IT team ahead of the outage and scheduled the phone system maintenance with its vendor
  • Checked that every system was healthy before shutdown, then powered down in order: phone system, PC peripherals, network devices, UPS
  • Restarted in the reverse order on the next working morning, before staff arrived
  • Validated wired and wireless networks, email, internet and intranet, printing, fax, the door security system and phones, then told users the work was complete