Shut down and restart all IT equipment at a distribution warehouse around the building's annual power maintenance, timed so warehouse operations were not interrupted.
- Notified warehouse users and the regional IT team, and confirmed the procedure and validation list beforehand
- Waited for each floor to finish the day's operations, then shut down servers, network devices, the UPS, printers and the time recorder in order
- Returned on the evening of the maintenance day, started the UPS first, then network equipment and servers, and checked for alarms
- Validated wired and wireless LAN, server and file share access, business applications, email, label printers, phones and fax, then sent a recovery notice and stayed on remote standby the next morning